|
|
(Click on Subject) Meeting of June 8, 2005 - At Yerington Weed Heights Community Hall Agenda - (Only Items Checked Were Covered)
Notes of Interest As Taken By Webmaster
Anaconda Copper Mine/Yerington - June 8th Stakeholders Meeting Summary for Site Activities since Last Meeting Unilateral Administrative Order (Order) for Initial Response Actions
Current Status of Required Actions under Order
To be included in Site General Work Plan due on June 1, 2005 – ARC has
contracted AHI to provide site security – Site personnel previously working
for SRK have been hired by AHI and site office has been moved to Weed
Heights
ARC provided updated Site Health and Safety Plan in May 12th
Notice of Intent to Comply – ARC to also provide summary of radiological
screening conducted under Process Areas field work by B&C and consultants
Rocky Mountain Environmental Consultants, Bartlett, and by AHI during
groundwater sampling and pumpback system maintenance
To be included in Site General Work Plan due on June 1, 2005 - On May 24,
2005 ARC provided responses to EPA’s December 21, 2004 review comments on
Draft Air Quality Monitoring Work Plan and on EPA’s May 6, 2005 response to
ARC’s March 10, 2005 letter regarding the EPA December 21, 2004 review
comments. Substantial differences in technical approach remain between EPA
and ARC and will have to be resolved before work plan approval is granted.
Work plan to be provided 30 days after Site General Work Plan is approved. ARC has proposed to compile all available radiological data for site by June 30th if data is provided by June 1st. ARC proposed an evaluation of the compiled data over a 3 to 4 month period after which a submittal date for the draft work plan would be proposed. On May 24, 2005, EPA and ARC held a conference call regarding the scope for the radiological survey. Based on the call substantial differences in technical approach remain between EPA and ARC and will have to be resolved before work plan approval is granted. ARC will provide to EPA the proposed approach in writing by mid-June 2005. In the interim to address potential radiological contamination in mine
materials used off site in residential, institutional and general
construction EPA conducted a screening level survey using the Las Vegas
lab’s scanner van during April 18 to 27, 2005. No anomalous radiation beyond
the area’s background was found over roughly 200 miles of survey other than
previously know anomalies on the mine site.
To be included in Site General Work Plan due on June 1, 2005. On March 1,
2005, EPA and their Las Vegas Emergency Response Team, BLM, NDEP, and ARC
conducted a site tour of the Arimetco heap leach pad fluids management
system to assess the current conditions and any necessary renovation or
recommendations which will be included in the Site General Work Plan
Status of ongoing work summarized by ARC in May 4, 2005 letter. Process Areas field work complete and 3 monitoring wells installed as part of investigation will be sampled as part of the June 2005 quarterly groundwater monitoring round – Hydrogeologic Framework Assessment Anaconda Copper Mine / Yerington Work in Progress – Under Unilateral Administrative Order for Initial Response Actions, dated March 31, 2005 On Site Areas Process Areas – Soil and Groundwater Sampling (report in June/July?) Air Monitoring on Site Perimeter (issues remain on analytes) Quarterly and Annual Groundwater Monitoring of Monitoring Wells (next round in June) Operation and Maintenance of Pumpback System (O & M Manual – June 1st) Operation and Maintenance of Arimetco Heap Leach Fluids Management System (O & M Manual – June 1st)
Off-Site Areas Quarterly Domestic Well Sampling for the Radionuclides and Annual Domestic Well Sampling for Metals (next round in June) Provision of Bottled Water to Residents with wells exceeding uranium MCL Survey of off site mine materials for radiological contaminants (EPA report in June) Hydrogeologic Framework Assessment North of the Mine Site (approval by May 9th)
Work to be Started in the next Quarter On site Areas Site Security Improvements (estimated to be in June 2005)
On site and off site Assessment Site Wide and Adjacent Off Site Areas Radiological Site Assessment (Data compilation by June 30th, work plan 60 to 90 days? Later)
Work to be Conducted under Site Wide Remedial Investigation/Feasibility Study Administrative Order on Consent - start date to be determined in negotiations this summer Assess soil, and groundwater contamination and air quality (fugitive dust) in the following areas: (assumed priorities in 3 levels A,B,C for work plan)
On site Areas Process Areas Phase II (A Priority) Pit Lake (B Priority) Evaporation Ponds (B Priority) Sulfide Tailings(B Priority) Waste Rock Piles/ Oxide Leach Tailings (B Priority) Arimetco Heap Leach Pads – assessment and closure (C Priority) Arimetco SX/EW Plant and associated facilities(C Priority) On site underground storage tank investigation (B Priority)
On site and off site Assessment Evaluation of Interim Measures (A Priority) Fugitive Dust Assessment (A Priority) Wabuska Drain Phase II (B Priority) Site wide Groundwater Conditions (A Priority) Human Health and Ecological Risk Assessment/ in conjunction with reuse plan (C Priority)
Feasibility Studies for Possible Operable Units: Domestic Wells with Radiological Contaminants Operable Unit (if needed) Soils Operable Unit (would include fugitive dust/evaporation ponds/waste rock piles/ and heap leach pads) Process Areas Operable Unit Groundwater Operable Unit Site Wide Radiological Operable Unit Pit Lake Operable Unit Wabuska Drain Operable Unit
Also Engineering Evaluation/Cost Analysis for Interim Remedies – as appropriate Proposed Plans for the above OUs Record of Decisions for the above OUs
|